 |
 |
| Report
of Design Sub-Committee of the Residential Foundation Committee Texas
Board of Professional Engineers |
| Revised:
August 25, 2000 |
Note: Some of the mathematical
symbols used in this report have been changed from the original format
for Internet purposes)
1.0 INTRODUCTION
Approximately 1/2 to 1 billion dollars
is spent per year in the state for construction of residential foundations.
Their function is to properly support a residential structure without
permitting unusual distress or unsafe conditions to occur. The vast majority
of foundations constructed in Texas consist of shallow, stiffened and
reinforced slab on ground foundations. Many of these foundations have
to be placed on expansive clays or fills, which must be stable to adequately
support the foundation. Other types of foundations include suspended pier
and beam, pier and beam constructed on grade, and strip or spread footing
type foundations.
The situation of residential foundations
which are slab on ground in contact with expansive clay soils creates
one of the most complex design problems to be encountered in structural
engineering. The problem is a soil structure interaction problem with
the added complexity of the soil support conditions changing in response
to environmental factors. In this context of technical complexity it is
easy for inadequate design procedures or no design procedures to be utilized.
The results of poor design and construction of a foundation are sometimes
not noticed for several years after the construction is completed.
Because engineered foundations are not
required by typical building codes for residential structures, many houses
are constructed each year without benefit of engineering input. When such
un regulated structures are placed on problem sites considerable financial
loss can occur including over design, and distress of structures. This
report addresses the three problems of lack of engineering requirements,
inadequate engineering and poor construction phase practices with regard
to residential foundations.
It is not the intent of this report
to provide a prescriptive process for design of residential foundations,
but to present a methodology which will produce a professional service.
Other methods which produce comparable results could be used.
2.0 RECOMMENDED ACTIONS OF CITY AND
COUNTY BUILDING OFFICIALS
It is recommended that the Board of
Registration encourage local and state legislation promoting the inclusion
in local building codes of a requirement for engineered foundations for
residences on sites where any of the following conditions exist: the weighted
PI using a weight of 3 for upper 5 feet, 2 for middle 5 feet and 1 for
lower 5 feet or the PI of the upper three feet, which ever is greater,
has a value greater than 20, the site settlement potential exceeds one
inch under the expected structure loads, the structure will be structurally
supported over man made fill, the PVR is greater than 1 inch, or sites
with geologic hazards. If any of the above conditions exist, the local
officials should require an "engineered foundation" as defined
below.
3.0 MODEL STANDARD OF PRACTICE
3.1 Definition of "Engineered Foundation"
An engineered foundation is defined as one for which design is based
on adequate site specific geotechnical information embodied in a report
and prepared by a geotechnical engineer; the design of the foundation
is performed by a foundation or structural engineer; and construction
phase activities are observed with proper documentation.
3.2 Design Professional's Roles and Responsibilities
The geotechnical investigation and report shall be conducted under the
supervision of and properly sealed by a geotechnical engineer. The design
of the foundation shall be performed by a foundation or structural engineer
and sealed by that person. The geotechnical and structural engineering
may be performed by the same individual, provided that individual is
sufficiently qualified in both disciplines.
The foundation design engineer will be the foundation engineer of record
and this individual shall be responsible for performing the construction
phase observations personally, by staff members under his direct supervision,
or by outside agencies who are under his direct control. Quality control
testing of construction materials as required by the foundation plans,
may be provided by an independent testing laboratory, employed by others,
provided reports are provided to the foundation engineer of record.
The foundation engineer of record shall issue a compliance letter at
the conclusion of construction activities stating that, to the best
of his knowledge, the foundation was constructed in substantial accordance
with the plans and specifications and any authorized modifications.
Any modifications, additions, or alterations to the construction of
the foundation shall be done by proper change order or modification
authorized by the foundation engineer of record.
3.3 Geotechnical lnvestigation
3.31 Information to be Assembled by Geotechnical
Engineer
Prior to laying out the investigative program, the
geotechnical engineer will obtain the following, when available: a plat
or map of the subdivision, local topography maps, aerial photographs,
the existing grades and proposed final grading plan, geological outcrop
maps, fault maps (if appropriate), soil conservation service report,
and general information concerning the characteristics of the structures
to be built.
3.32 Minimum Field Investigation Program
The geotechnical engineer will lay out the proposed
investigative program including the location and depths of borings,
sampling procedures and laboratory testing required. A minimum investigative
program for subdivisions shall cover the geographic and topographic
limits of the subdivision, and shall examine believed differences in
geology in sufficient detail to provide information and guidance for
secondary investigations, if any. As a minimum standard for believed
uniform subsurface conditions borings shall be placed at a maximum 300
foot centers across a subdivision. Non uniform subsurface conditions
may require additional borings. A single lot investigated in isolation
shall have a minimum of one boring or more placed as determined jointly
by the geotechnical engineer in consultation with the foundation engineer.
Borings should be a minimum of 15 feet in depth unless confirmed bedrock
is encountered at less depth. In certain circumstances, some borings
should be placed near trees to obtain depths of probable root penetration.
Borings shall extend through any fill or potentially compressible materials
even if greater depths are required. All borings shall be sampled by
either augured samples or semi disturbed samples at a minimum interval
of one per two feet of boring in the upper 10 feet and at 5 foot intervals
below that. Borings shall either be sampled and logged in the field
by a geotechnically trained professional or all borings shall be sampled
as described such that a geotechnical engineer may examine and confirm
the driller's logs in the laboratory.
Investigative borings may either be by drill rig
or by test pit provided the depth requirements are satisfied.
Sites which are obviously rock with outcrops showing
or easily discoverable by shallow test pits may be investigated and
reported without resort to drilled borings.
Presence of roots shall be logged by depth in all
borings.
Intermittent or aquifer water levels shall be noted
in borings that indicate groundwater and if material to needs of the
project. Observations shall be based on a minimum of one hour observation
of the bore holes or pits.
During the field investigations, sketches shall be
made of the apparent extent of fill, seepage areas, major vegetation
and approximate slopes. The presence of fence lines, old roads or trails
or other manmade constructions should also be noted in addition to the
borings.
If appropriate, fault studies shall be performed.
3.33 Minimum Laboratory Testing Program
Sufficient laboratory testing shall be performed
to identify all significant strata found in the borings across the site.
Testing need not be done in every boring provided sufficient correlation
can be obtained between borings by a qualified geotechnical professional.
Characterization of each significant stratum shall include the moisture
content profiles, Atterberg limits, laboratory or field penetrometer
estimates of cohesion and the Unified System classification. Additional
testing required for each significant stratum will include hydrometer
testing to determine the percent fine clay (2 micron size) and the #200
sieve size percentage.
At least one volume change/pressure relationship test is recommended
to be performed for each significant clay stratum if deemed necessary
by the geotechnical engineer. On sites with more than seven feet of
expansive clay soils, defined as having plasticity indices greater than
20, it is recommended that at least 1 out of every 10 borings have sufficient
samples obtained to provide an in situ moisture content test and soil
suction test at two foot intervals to the entire depth of the boring.
All laboratory testing shall be generally in accordance
with ASTM Standards.
3.34 Site Characterization
The geotechnical engineer shall characterize the
site for design purposes. If shallow foundations are recommended, report
for each lot in the project the Soil Support parameters (including em
and Ym for edge and center lift modes) as found in Appendix "A",
bearing capacity and the presence and condition of fill. In addition,
the geotechnical report shall indicate the approximate slopes of each
lot and discuss whether downhill creep or other instability may be present.
Vegetation shall be noted as well as other visible or known features
such as seeps, manmade improvements, fence lines or other linear features
and their impact on design. If the site is subject to settlement, an
estimate shall be made of the probable settlement based on the proposed
structure loading and soil properties. In lieu of the above recommendations,
alternate recommendations may be provided by the geotechnical engineer
if so requested by the foundation engineer.
The Soil Support parameters shall be developed by calculation using
formulations compatible with the principles of unsaturated soil mechanics.
Refer to Appendix A for an acceptable technique. These procedures are
applicable to all types of shallow foundations on expansive soils, whether
reinforced with re bars or post tensioning.
If pier and beam foundations are to be recommended,
the bearing capacity and establishment depth of piers shall be calculated
and values of skin friction or alternate reinforcing steel shall be
recommended to be used in uplift and down drag calculations as well
as bearing analysis of the piers shall be calculated. The piers shall
be anchored below the depth where t vertical movement is calculated
to be zero or this depth may be based on extensive local experience
based on measurements. This depth will be greater within the root zones
of major vegetation.
Lateral pressures to be applied in design of retaining
type structures shall be determined by the geotechnical engineer.
3.35 Geotechnical Report
Geotechnical reports shall contain, as a minimum,
an introduction of the project, the investigative procedures, the laboratory
testing procedures utilized, the results of laboratory testing, the
geologic conditions, slopes, logs of borings and plans showing boring
location, a plan showing areas of probable fill in existence at the
time of the investigation and, as appropriate, other features such as
seeps, vegetation or lineations and man made structures.
Reports shall contain specific recommendations for
the foundation engineer to use for the design of foundations for each
lot on the project, including suitable foundation types and, ( as appropriate,
the Soil Support parameters for each lot, shallow bearing values, deep
foundation bearing and skin friction as well as depth of establishment,
lateral pressures for use in designing retaining structures or deep
grade beams, and other specific recommendations concerning site construction.
Sufficient geotechnical data shall be included to permit the foundation
engineer of record to adjust design inputs for specific needs of the
design. In lieu of the above recommendations, alternate recommendations
may be reported if requested by the foundation engineer. The report
shall be prepared, signed and sealed by a geotechnical engineer.
3.36 Fill
The presence and methods of dealing with existing
and proposed fill to be placed during construction shall be discussed
by the geotechnical engineer in his report. Fill criteria useful for
design and construction of residential foundations may be seen in Appendix
B.
3.4 Design of Foundations
3.41 Information to be Assembled by Foundation Engineer
The foundation engineer shall assemble or be provided
by his client the subdivision plan, the topography of the area including
original and proposed final grades, the geotechnical report, the architectural
floor plan of the structure and sufficient additional architectural
information to determine the magnitude, construction materials and location
of structural loads on the foundation. If exposed or architectural concrete
is to be used in finished concrete surfaces, this information should
be provided to the foundation engineer.
3.42 Design Procedures
The foundation engineer shall utilize a procedure
that will provide designs that will meet minimum criteria of either
the Standard Building Code 1997 Section 1804.3.3.3 or Uniform Building
Code 1997 Section 1815, 1816, for the design of slab on ground foundations
for potentially expansive clay sites. Geotechnical procedures shall
be those of Section 3.
Foundations utilizing piers with suspended slab and
beams shall be designed by building code procedures.
Soil supported slab on ground foundations with piers
shall be designed as a stiffened slab on ground by above procedures
and piers shall not be attached to the slab or grade beams.
Permissible design deflection
ratios of residential foundations shall meet the following criteria:
| Construction
|
Permissible
Foundation Deflection Ratios |
| Masonry
Walls |
1 /800 |
| Sheetrock
Interior Walls
Edge or Center Lift Mode |
1/480 |
| Full Span
Roof Trusses
Edge Lift Mode |
1 /960 |
Deflection
ratio is defined as (A)/L where (A) is the vertical movement at the
center of a symmetrical bowl shaped depression or. mound and L is the
distance from side to side of the considered depression or mound.
Foundations which will span
between piers, or slab panels which span between stiffener beams or
perimeter beams or other points of load transfer, shall be designed
to meet the above deflection criteria assuming all dead loads and live
loads.
3.43 Minimum Plan and Specification
Information
The engineer's drawings shall
show a plan view of the foundation locating all major structural components
and reinforcement. Details shall be shown to indicate construction and
dimensions of stiffener beams, piers, retaining walls, drainage details,
etc.,if such features are integral to the foundation. Drawings shall
contain sufficient information for the proper construction and observation
by field personnel. Specifications shall include the reinforcing or
pre stressing cables and hardware; concrete specifications including
compressive strengths; notes concerning existing or proposed fill, nearby
existing and known future vegetation and the required design features
to accommodate these conditions; and the schedule of required inspections.
Minimum perimeter and lot drainage requirements shall
be shown or noted on the plan.
Plans shall be specific for each site or lot
location and shall include the client's name and engineer s name, address
and telephone number and the geotechnical data and source used.
3.44 Foundation Engineer's Specification for Fill
The foundation engineer's plans shall address fill
existing at the time of the design or to be placed during construction
of the foundation and shall require any fills which are to support the
bearing elements of the foundation to be tested and approved by a geotechnical
engineer assisted by a qualified laboratory. Bearing elements of a suitably
designed slab on ground foundation are defined as the bottoms of exterior
or interior stiffener beams. Such approval shall include a summary report
by the geotechnical engineer of the methods and results of investigation
and testing that were used and a statement that the existing or placed
fills are suitable for support of a shallow soil supported slab on ground
or that the foundation elements should penetrate the fill to undisturbed
material. See also Appendix B for more detailed information on fills.
3.5 Construction Phase Observation
3.51 Responsibility for Observations
The foundation engineer of record will be responsible
for performing observations of construction personally or having them
performed by a staff member under his direct supervision or by an independent
third party agency qualified to do such observation, which reports to
the foundation engineer of record. In any event, the responsibility
for issuing the final compliance report shall rest with the foundation
engineer of record. Fills which are to support bearing elements of a
foundation shall be tested and approved by a geotechnical engineer,
assisted by a qualified laboratory.
3.52 Minimum Program of Observation
At a minimum, foundations should be inspected as
applicable to see that fill conditions are satisfied in, accordance
with the plans and specifications; piers are observed for proper placement
and depth, concrete and reinforcing installation; observation of all
foundation elements immediately before concrete placement; observation
of concrete placement; and a stressing observation noting and comparing
the elongation of each cable to the calculated elongation and the stressing
load applied to each cable.
3.53 Compliance Letter
At the satisfactory accomplishment of all the requirements
of the plans and specifications, the foundation engineer of record shall
provide a letter to the client indicating the geotechnical data and
source used in the design; the design procedures used; the construction
observation performed and results; and, as appropriate, a statement
concerning the methodology of dealing with fill, either by satisfactory
compaction compliance or by penetration; and the methodology of dealing
with slopes, vegetation and drainage. The letter shall conclude with
a statement that, in his opinion, the construction of the foundation
was in substantial conformance with the engineer's plans and specifications
including any modifications or alterations authorized.
4.0 REFERENCES
"Design and Construction of Post Tensioned Slabs
on Ground", 2nd Edition, (PTI Manual) Post Tensioninq institute,
Phoenix, 1996
American Society for Testing and Materials, West
Consholhocken, Pennsylvania.
Standard for Residential Foundations on Expansive
Clay (Draft), American Society of Civil Engineers, Reston, Virginia,
1999
"Prediction of Movement in Expansive Clay",
Vertical and Horizontal Deformations of Foundations and Embankments,
Geotechnical Special Publication No. 40, Lytton, R.L., Yeung, AT., and
F- Iio, G.Y., ed., ASCE, New York, New York, Vol. 2, 1827 1845, 1994.
Residential Foundation New Design Subcommittee
Members
Robert E Bigman, P.E.
Buchanan/Soil Mechanics, Inc.
Bryan/Texas
Robert C. Davis. P.E
Trinity Engineering Testing Corp.
Austin, Texas
David A. Eastwood. P.E.
Geotech Engineering & Testing Inc.
Houston, Texas
Richard Hale, P.E.
Perry Homes
Houston, Texas
Jim D. Mallory, P.E.
Safety Management Associates, Inc.
Hewitt, Texas
David Messersmith, AIA
Lubbock, Texas
Douglas S. Porter, P.E.
Round Rock, Texas
H. Platt Thompson, P.E.
Thompson Professional Group, Inc.
Houston, Texas
Kirby T. Meyer, P.E., Chairman
MLAW Consultants & Engineers
Austin, Texas
APPENDIX
A
Procedures
for Determining Soil Support Parameters For
Shallow Foundations on Expansive Soil Sites
(Revised
8 25 00 errata)
General
These support parameters arc equally applicable to all stiffened, reinforced
slab foundations, whether reinforced with conventional re bar steel or
post tensioning, constructed on expansive soil sites. Other procedures
may be used, provided comparable foundation designs are achieved.
Expansive Soil Sites
Sites for which this procedure is applicable should meet either of the
following criteria:
- Two feet or more of soil classified as CL
or CH by the Unified Soil Classification System having a PI of 20
or greater within the upper 5 feet of the soil profile.
- PVR (TxDOT 12413) calculated for the upper
9 feet using "Dry" initial conditions which is 1.0 inches
or greater The suggested depth oh 9 feet is for the purposes of screening
soil profiles to determine if the site is an "expansive soil
site" for which the remainder of this appendix is applicable.
If neither of these criteria is
met, the foundation should be designed as a non stiffened slab foundation,
such as the B.R.A.B. #33 or Post Tensioning Institute (1996) Type 11 foundations,
and the remaining procedures of this appendix arc not applicable.
Edge Moisture Variation Distance
(em)
The edge moisture variation distance is the distance beneath the edge
of a shallow foundation within which moisture will change due to wetting
or drying influences around the perimeter. In an edge lift case, the moisture
in the soil is higher at the edges than in the center. The center lift
case is one in which the moisture is higher in the center than the edges.
The major factor in determining the penetration distance is the unsaturated
diffusion coefficient, a. This, in turn, depends on the level of suction,
the permeability, and the cracks in the soil.. For the same diffusion
coefficient, the em value will be larger for the center lift case in which
moisture is withdrawn from moist soil under the center of the foundation.
The ell, value will be smaller for the edge lift case in which moisture
is drawn beneath the building into drier soil. Roots, layers, fractures
or joints in the soil will increase the diffusion coefficient and the
em value for both the edge lift and center lift conditions.
Using representative values based on laboratory
test results in each significant layer, the following parameters are required
to determine edge moisture variation distance, em,
and differential movement, Ym:
- Liquid Limit, LL
- Plastic Limit, PL
- Plasticity Index, PI
- Percentage of soil passing No.200 sieve (%
No.200)
- Percentage of soil finer than 2 microns (%
- 2 microns) expressed as a percentage of the total
sample.
- Percent fine clay (% 2 microns) / (%-#200)
reported as %fc, report as percentage.
For example : 45% / 80% = 0.56, report as 56%.
Calculate Yh
Yh, = Yo
(%fc / 100)
Terms: Yo is the change of soil volume for a change
in suction for 100% fine clay content.
Yh is the correction of Y
for the actual % of fine clay (%fc).
where Y is determined
using the following steps:
Step 1 Determine Mineral Classification
Zone 1, 11, 111 or IV from the chart below. If your data does not fall
within one of the four zones, use the nearest zone.
Step 2 Proceed to the chart corresponding
to the zone determined in Step 1 to determine Yo.
Differential Soil Movement (Ym)
Differential soil movement of the soil should be estimated using the change
in soil surface elevation at two locations separated by a distance eon
within which the differential movement will occur. An initial and a final
suction profile should be used at each of the two locations to determine
differential movement. For general analysis, the initial suction profile
should be the same at both locations.
The final suction profile at each location
should be determined from controlling suction conditions at the surface.
A one dimensional finite clement analysis of the layered profile with
measured or estimated suction profile envelope may be used to yield estimates
of movement for the purpose of design and analysis. A two dimensional
analysis maybe necessary to study the effects of trees, edge barriers,
flower beds, lawn watering or pipe leaks.
In absence of local observations,
controlling soil suction values at the ground surface are recommended
as follows:
- Wettest: 2.5 pF, if measured under soaking conditions,
which is typical of poor drainage or excessive watering
- Driest 4.5 pF, if the surface suction is controlled
by vegetation or 6.0 pF, if the surface suction is controlled by evaporation
from bare soil, or soil with wilted vegetation.
Controlling soil suction values
below the soil surface occur at depths that are remote from the surface
(Zm) and are as follows:
- High Water Table: 2.0 pF at the water table unless
there is a high osmotic component, in which case, the measured value
of suction should be used.
- Climate Controlled Suction: This suction may
be determined by measurement at a depth below which the suction varies
by less than 0.027 pF per ft. This is also the Zm
depth.
- Tree Root Zone: 4.5 pF under driest conditions,
when the tree is near the wilting point.
- High Osmotic Suction or Cemented Soil: these
suction values must be determined by measurement. Suctions at depths
that arc substantially different than those estimated by the suction
vs Thomthwaite Moisture Index curve on page 47 of Post Tensioned Institute
(1996) indicates dissolved salts in the pore water, and possible formation
from deposition in a marine environment, or cementation.
A typical vertical suction profile is
computed by using the principles of steady state unsaturated flow which
links the controlling suction values at the soil surface to the controlling
suction below the surface. The principles of steady state unsaturated
flow may be found in Lytton (1994).
Measures for estimating differential soil
movements should be computer methods used to generate the design values
of Ym for the edge lift and center lift conditions.
In the absence of computer methods,
the following table may be used to estimate approximate design values
of Ym. This method should only be attempted if atypical
soil suction profile is present at the beginning and ending conditions.
Otherwise, this procedure may not be conservative.
Measured
suction
(pF) at Depth Zm
|
Controlling
Suction At Surface, pF
|
| |
2.5 |
2.7 |
3.0 |
3.5 |
4.0 |
4.2 |
4.5 |
| 2.7 |
+3.2 |
0 |
-4.1 |
-13.6 |
-25.7 |
-31.1 |
-40.0 |
| 3.0 |
+9.6 |
+5.1 |
0 |
-7.5 |
-18.2 |
23.1 |
-31.1 |
| 3.3 |
+17.7 |
+12.1 |
+5.1 |
-2.6 |
-11.5 |
-15.8 |
-23.1 |
| 3.6 |
+27.1 |
+20.7 |
+12.1 |
+1.6 |
-5.7 |
-9.4 |
-15.8 |
| 3.9 |
+38.1 |
+-38.8 |
+20.7 |
+7.3 |
-1.3 |
-4.1 |
-9.4 |
| 4.2 |
+50.4 |
+42.1 |
-30.8 |
+14.8 |
+3.2 |
0 |
-4.1 |
| 4.5 |
+
63.6 |
+54.7 |
+42.1 |
23.9 |
+9.6 |
+5.1 |
0 |
Notes: The positive sign indicates heave
and the negative sign indicates shrinkage.
If suction profiles include the effects
of flower beds, poor drainage or tree root zones, this approximate procedure
is not valid
The estimated value of Ym
can be determined from
Ym Yh
mod x (Stress Change Factor from above table)
The modified value of Yh,
Yh mod, is the averaged volume
change coefficient of the soil supporting the slab. This should be calculated
as a weighted average of the Yh
values in each of the layers of soil to a depth of a minimum of nine feet.
Depths greater than nine feet may be used if justified by geotechnical
analysis. The yh values in the upper one third have a weight of three,
in the next third a weight of two, and in the bottom third a weight of
one. The sum of the products of layer thickness (feet), yh and weight
for all layers should be used to obtain the weighted average as the modified
value Yh mod., which is to
be used to estimate the Ym value for edge lift (positive value) and center
lift (negative value).
Barriers
Vertical moisture
barriers may be used to reduce the soil support parameters (em
and Ym) provided the barriers are properly designed
to virtually stop moisture migration to or from the under slab area on
a permanent basis.
The effect of
a barrier on em and Ym may
be estimated by the principles of unsaturated soil mechanics, most easily
by the use of a two dimensional moisture flow analysis computer program.
A vertical barrier should extend at least 2.5 ft below adjacent ground
surface to be considered as having any effect.
APPENDIX
B
Fill
Guidelines
FILL
Fill is frequently a factor in residential
foundation construction. Fill may be placed on a site at various times.
If the fill has been placed prior to the geotechnical investigation, the
geotechnical engineer should note fill in the report. Fill may exist between
borings or be undetected during the geotechnical investigation for a variety
of reasons. The investigation becomes more accurate if the borings are
more closely spaced. Occasionally, fill is placed after the geotechnical
investigation is completed, and it may not be detected until foundation
excavation is started.
If uncontrolled fill (see discussion below)
is discovered later in the construction process, for instance, by the
Inspector after the slab is completely set up and awaiting concrete, great
expense may be incurred by having to remove reinforcing and forms to provide
penetration through the fill. Therefore, it is important to identify such
materials and develop a strategy for dealing with them early on in the
construction process. Fill can generally be divided into three types:
Engineered
fill
Forming
fill
Uncontrolled
fill
Engineered fill is that
which has been designed by an engineer to act as a structural element
of a constructed work and has been placed under engineering inspection,
usually with density testing. Engineered fill may be of at least two types.
One type is "embankment fill," which is composed of the material
randomly found on the site, or imported to no particular specification,
other than that it be free of debris and trash. Embankment fill can be
used for a number of situations if properly placed and compacted. "Select
fill" is the second type of engineered fill. The term "select"
simply means that the material meets some specification as to gradation
and P.I., and possibly some other material specifications. Normally, it
is placed under controlled compaction with engineer inspection. Examples
of select fill could be crushed limestone, specified sand, or crusher
fines which meet the gradation requirements. Select underslab fill is
frequently used under shallow foundations for purposes of providing additional
support and stiffness to the foundation, and replacing a thickness of
expansive soil. Engineered fill should meet specifications prepared by
a qualified engineer for a specific project, and includes requirements
for placement, geometry, material, compaction and quality control.
Forming fill is that
which is typically used under residential foundation slabs and is variously
known as sandy loam, river loam or fill dirt. Forming fill is normally
not expected to be heavily compacted, and no wise designer will rely on
this material for support. The only requirements are that this material
be non expansive, clean, and that it works easily and stands when cut.
If forming fill happened to be properly compacted and inspected in accordance
with an engineering specification it could be engineered fill. When designing
a foundation for this type of fill, the beam bottoms must penetrate it
completely and slab panels should be designed to span between beams if
more than 48" will exist below the slab panels.
Uncontrolled fill
is fill that has been determined to be unsuitable (or has not been proven
suitable) to support a slab on ground foundation. Any fill that has not
been approved by a qualified geotechnical engineer in writing will be
considered uncontrolled fill. Uncontrolled fill may contain undesirable
materials and/or has not been placed under compaction control. Some problems
resulting from uncontrolled fill include gradual settlement, sudden collapse,
attraction of wood ants and termites, corrosion of metallic plumbing pipes,
and in some rare cases, site contamination with toxic or hazardous wastes.
BUILDING
ON FILL
To
establish soil supported foundations on fill, the typical grid beam, stiffened
slab foundation is required to penetrate through forming fill or uncontrolled
fill with the perimeter and interior beam bottoms forming footings. Penetration
will take the load supporting elements of the foundation below the unreliable
fill. Penetration could be done by deepened beams, spread footings or
piers depending on the depth and the economics of the situation. Generally,
piers are most cost effective once the fill to be penetrated exceeds about
3 feet, but this depends on the foundation engineer's judgment and local
practice.
Pre-existing,
uncontrolled fill can be approved through proper investigation by the
foundation engineer or a geotechnicall engineer. The approval may depend
on whether or not the fill is fairly shallow, free of trash, the age of
the fill, and the results of testing and proof rolling. These procedures
should be performed under the observation and approval of the engineer,
who must be able to expressly state after his investigation that the fill
is capable of supporting a residential slab on ground foundation.
|